10 exam-style questions with answers and explanations, straight from our 1,030-question bank. Tap an answer to check yourself. When you're ready, take the scored version in the free practice test.
Two independently valved air banks are labeled PRIMARY and RESERVE. Both feed one pressure-reducing regulator, then the diver's supply panel. The gas is correct, and each bank contains enough usable air for the planned contingency. What modification would keep the reserve available if that regulator failed shut?
Show answer & explanation
Correct answer: B - Give the reserve a separate regulated route to a dedicated panel inlet.
Question 2
For a no-stop surface-supplied dive, the recovery plan requires 18 minutes of emergency gas at 66 fsw, including all contingency allowances. A cylinder has a 12-L water capacity and a pressure of 200 bar; gas below 50 bar cannot be credited. Emergency breathing demand is 40 surface liters per minute. Use a linear ideal-gas estimate, a 1-bar surface pressure, and 33 fsw per added atmosphere. Delivery performance and temperature allowances have been verified. Which assessment of the cylinder's usable gas is correct?
Show answer & explanation
Correct answer: D - 15 minutes; not enough for the planned recovery.
Question 3
Two divers supplied by the same compressor develop headache and nausea. After recovery, both have SpO2 readings of 99% on conventional two-wavelength pulse oximeters. A wind shift had carried generator exhaust toward the compressor intake. Which interpretation should guide their assessment?
Show answer & explanation
Correct answer: A - Carbon monoxide poisoning remains possible despite the apparently normal oxygen saturation.
Question 4
A screened intake connects a reservoir to a lower wet well. The pump motor is locked out, but an open bypass still allows water to pass between the two levels. No current is visible from topside. The plant operator considers the intake safe for a diver inspection because the pump cannot start. What hazard has that assessment missed?
Show answer & explanation
Correct answer: C - Gravity-driven flow can persist between the unequal water levels and create a dangerous pressure differential at the intake.
Question 5
A revised work scope changes an 85-fsw inspection from a no-stop dive to a planned-decompression operation. One diver will be working, and the assessment identifies no task-specific need to exceed ADCI's minimum staffing. Before approving the revised plan, which personnel and chamber arrangement must the supervisor secure?
Show answer & explanation
Correct answer: A - Five people, including a standby diver and two tender/divers, with an operational double-lock chamber on site.
Question 6
At the morning check, two equivalent pneumofathometer gauges are exposed to the same test pressure. Both have a 0-250 fsw scale; one reads 88 fsw and the other 96 fsw. Their scheduled six-month calibrations are not yet due. Under 29 CFR 1910.430(g), how should the supervisor handle this discrepancy?
Show answer & explanation
Correct answer: C - Have the gauges deadweight-tested or calibrated against a master reference before relying on them.
Question 7
The dive log records: leaves surface 09:12; reaches the work 09:16; stops the tool 09:37; leaves bottom for the final ascent 09:42. The job is at 74 fsw, but the diver briefly reached 82 fsw while positioning. The approved square-profile procedure uses actual maximum depth and elapsed time from leaving the surface to starting the final ascent. Which unrounded depth and bottom-time inputs belong in the decompression calculation?
Show answer & explanation
Correct answer: D - 82 fsw and 30 minutes.
Question 8
After only three minutes at 18 fsw on air, a diver makes an uncontrolled ascent while holding their breath. Within one minute of surfacing, the diver develops difficulty speaking and weakness of one arm. Emergency oxygen and medical activation are already underway. What mechanism best explains this presentation?
Show answer & explanation
Correct answer: B - Pulmonary overexpansion has ruptured lung tissue and introduced gas into the arterial circulation.
Question 9
For an underwater steel cut, the return clamp has been attached to a separate section of structure. The anticipated current path would pass through the diver's working position. The DC source and topside safety disconnect have passed their checks. Which setup change addresses the identified electrical hazard?
Show answer & explanation
Correct answer: D - Connect the return directly to the work with the diver outside the intended current path.
Question 10
A crane will raise a solid assembly from seawater and land it on deck. The assembly weighs 4,000 lbf in air and displaces 40 ft³ of water. Use a seawater weight density of 64 lbf/ft³. The crane's verified capacity is 3,000 lbf at every radius used in this lift. Neglect rigging weight, dynamic loads, and seabed suction for this check. How does the air-water transition affect approval of this lift?
Show answer & explanation
Correct answer: A - 1,440 lbf submerged and 4,000 lbf clear of the water; the crane cannot complete the lift.
That's 10 of 1,030